Which process ensures that provision has been made to address any open issues of risks, with follow- seenagape 9 years ago Which process ensures that provision has been made to address any open issues of risks, withfollow-on action recommendations? A.Closing a Project B.Controlling a Stage C.Directing a Project D.Initiating a Project ← Previous question Next question →