PRINCE2 Exam Questions

Which process covers the activities of those at the level of management above the Project Manager?

Which process covers the activities of those at the level of management above the Project
Manager?

A.
Controlling a Stage

B.
Managing a Stage Boundary

C.
Directing a Project

D.
Managing Product Delivery