Which process controls the link between the Project Manager and the Team Manager(s)? seenagape 9 years ago Which process controls the link between the Project Manager and the Team Manager(s)? A.Controlling a Stage B.Managing a Stage Boundary C.Managing Product Delivery D.Directing a Project ← Previous question Next question →