Which PRINCE2 role has a specific responsibility for checking that the project remains aligned to th

Which PRINCE2 role has a specific responsibility for checking that the project remains aligned to
the corporate or programme strategy?

A.
Project Manager

B.
Project Assurance

C.
Senior User

D.
Senior Supplier