Which of the following would be done once the Project Board have authorized initiation?

Which of the following would be done once the Project Board have authorized initiation?

A.
Create the initiation Stage Plan

B.
Establish who needs information, when and in what format

C.
Establish the quality expectations of the customer

D.
Define how the project will deliver the chosen business solution