Which of the following statements about quality assurance and Project Assurance is true?

A.
Project Assurance is the responsibility of the corporate organization; quality assurance is
the responsibility of the Project Board
B.
Project Assurance is independent of the Project; quality assurance is only independent of
the Project Manager
C.
Project Assurance may be delegated within a project; quality assurance must be
undertaken by the Project Board
D.
Project Assurance ensures compliance to standards within the project environment;
quality assurance ensures compliance across the organization