Which of the following options describes those stages?

There should be at least two management stages in a PRINCE2 project. Which of the following
options describes those stages?

A.
Initiation as the first stage, the remainder of the project as the second stage

B.
Initiation as the first stage, closure activities as the second stage

C.
Procurement as the first stage, design and implementation as the second stage

D.
Pre-project work as the first stage, initiation as the second stage