PRINCE2 Exam Questions

Which of the following is used to inform the Project Board of a forecast deviation of stage-level to

Which of the following is used to inform the Project Board of a forecast deviation of stage-level
tolerance?

A.
Exception Plan

B.
Exception Report

C.
Off-specification

D.
Lessons Report