Which of the following is used to inform the Project Board of a forecast deviation of stage-level to seenagape 7 years ago Which of the following is used to inform the Project Board of a forecast deviation of stage-leveltolerance? A.Exception Plan B.Exception Report C.Off-specification D.Lessons Report ← Previous question Next question →