Which of the following is NOT within the authority of the Project Board? seenagape 8 years ago Which of the following is NOT within the authority of the Project Board? A.Approve the End Project Report B.Set Stage-level tolerance C.Approve Stage Plans D.Set project-level tolerance ← Previous question Next question →