Which of the following is NOT a purpose of the Closing a Project process?

A.
Plan the activities required to close a project
B.
Enable a comparison of the original objectives of a project against what was actually
achieved
C.
Enable premature closure if the Project Board request that a project should no longer
continue
D.
Provide a fixed point at which acceptance for the project product is confirmed
Explanation:
The answer A is right, Managing Successful Projects With PRINCE2, Sections 18.1, 18.3
0
0
Option A is the correct:
Explanation: As seen in 18.3 of the PRINCE2, 2009 book “Closure activities should be planned as part of the Stage Plan for the final management stage. ” it means activities for Project closure is planned at the stage before the closure it self.
4
0