Which of the following is NOT a PRINCE2 Principle? seenagape 11 years ago Which of the following is NOT a PRINCE2 Principle? A.Continued business justification B.Project manage by process C.Manage by stages D.Tailor to suit the project environment ← Previous question Next question →