Which of the following is FALSE regarding an Exception Report?

Which of the following is FALSE regarding an Exception Report?

A.
It describes a forecast deviation of stage or project level tolerance

B.
It contains recovery options and a recommendation

C.
It replaces a Stage Plan or Project Plan

D.
It describes the consequences of the deviation