Which of the following is a specific objective of the Controlling a Stage process?

Which of the following is a specific objective of the Controlling a Stage process?

A.
Attention is focused on delivery of the stage’s products

B.
Assure the Project Board that all products in the Stage Plan for the current stage have been
completed and approved

C.
Work on products allocated to the team is authorized and agreed

D.
The various ways the project can be delivered are evaluated and a project approach selected