Which of the following describes the recommended minimum number of stages?
A.
Initiation as the first stage, the remainder of the project as the second stage
B.
Initiation as the first stage, closure activities as the second stage
C.
Procurement as the first stage, design and implementation as the second stage
D.
Pre-project work as the first stage, initiation as the second stage