PRINCE2 Exam Questions

Which of the following describes risk proximity?

Which of the following describes risk proximity?

A.
The timeframe over which the risk mitigation actions should be implemented

B.
The schedule for the risk management activities related to a plan

C.
The timeframe over which a risk will be monitored by the risk owner

D.
The timeframe for when the risk might materialize