which of the following are the aspects of project performance to be managed? seenagape 11 years ago According to PRINCE2, which of the following are the aspects of project performance to bemanaged? A.Processes, themes, principles B.Time, cost, quality, people C.Time, cost, quality D.Time, cost, quality, scope, benefits, risk ← Previous question Next question →