The purpose of the Progress theme is to do which of the following?

A.
Identify, assess and control uncertainty

B.
To establish mechanisms to monitor and control what has happened against what is planned

C.
Facilitate communication and control by defining the means of delivering the products

D.
Define and implement the means by which the project will create and verify products which are
fit for purpose