which Management product would the Project Board specify where the authority for change requests lie seenagape 11 years ago In which Management product would the Project Board specify where the authority for changerequests lies? A.Risk Management Strategy B.Quality Management Strategy C.Communication Strategy D.Configuration Management Strategy ← Previous question Next question →