Which management level uses the mechanisms included within the Progress theme to control any unaccep

Which management level uses the mechanisms included within the Progress theme to control any
unacceptable deviations?

A.
Only the Project Board

B.
Only the Project Manager

C.
All levels of management

D.
Only corporate or programme management