PRINCE2 Exam Questions

Which is the Change Authority role permitted to authorize?

Which is the Change Authority role permitted to authorize?

A.
Changes to the project that do not exceed a defined budget

B.
Risks to the project

C.
Adjustments to the limits on the change budget

D.
Changes to stage tolerance

Explanation: