Which is performed as part of the recommended risk management procedure?

Which is performed as part of the recommended risk management procedure?

A.
Allocation of a budget to investigate issues facing the project

B.
Review of risk management practices to ensure that they are performed effectively

C.
Sending of information about risks to the project to project stakeholders

D.
Resolution of conflicts between the project and the programme board