Which is part of the PRINCE2 definition of a project?

A.
A description of what must be delivered in order to gain acceptance
B.
The total of a plan’s products
C.
An undertaking that consists of at least two management stages
D.
A temporary organization that is created for the purpose of delivering business products
The answer D is right, Managing Successful Projects With PRINCE2, Section 1.3