Which is NOT undertaken during the Initiating a Project process?

A.
Identify if the project is sufficiently aligned with corporate objectives
B.
Show how the outcome is to be achieved
C.
Review why the project is needed
D.
Appoint an Executive and Project Manager
The answer is D.