Which is NOT one of the levels of plan recommended by PRINCE2? seenagape 9 years ago Which is NOT one of the levels of plan recommended by PRINCE2? A. Team Plan B. Benefits Review Plan C. Project Plan D. Stage Plan Explanation: ← Previous question Next question →