Which is NOT one of the levels of plan recommended by PRINCE2? seenagape 10 years ago Which is NOT one of the levels of plan recommended by PRINCE2? A. Team Plan B. Benefits Review Plan C. Project Plan D. Stage Plan Explanation: ← Previous question Next question →