Which is NOT a purpose of the Organization theme?

A.
Define the level of tolerance for each level of the project management team
B.
Define the Project Board’s responsibility for directing the project
C.
Define a project management team structure
D.
Define which role is accountable for the project’s success
The answer A is right, Managing Successful Projects With PRINCE2, Sections 5.3.2.1, 5.3.2.2