Which is an objective of the Starting up a Project process?

A.
Identify who will be responsible for creating the Project Plan
B.
Agree how issues and changes will be identified, assessed and controlled
C.
Agree how the project will be monitored and controlled after initiation
D.
Authorize the Project Manager to proceed with the initiation stage
The answer A is right, Managing Successful Projects With PRINCE2, Sections 12.2, 12.4