Which is an objective of the Controlling a Stage process?

Which is an objective of the Controlling a Stage process?

A.
Prepare a Stage Plan for the next stage

B.
Make arrangements to address all open issues and risks, with follow-on action
recommendations

C.
Obtain approvals for completed products

D.
Prevent scope creep’ by monitoring products for uncontrolled change