Which is a responsibility of the managing level within the project management team?

Which is a responsibility of the managing level within the project management team?

A.
Approve stage completion

B.
Ensure that the products are produced within the constraints agreed with the Project

Board

C.
Set project tolerances

D.
Appoint the project management team