Which is a responsibility of the managing level within the project management team?

A.
Approve stage completion
B. Board
Ensure that the products are produced within the constraints agreed with the Project
C.
Set project tolerances
D.
Appoint the project management team
all answer appear green. Which one is right? Viewed on an Ipad, safari
0
0
B
1
0
It seems that the right answer is B.
1
0
The right answer is B, Managing Successful Projects With PRINCE2, Section 5.3.1