Which is a purpose of quality planning?

A.
Detail the acceptance criteria, in order for the Project Board to agree the level of quality
expected of the project’s product
B.
Document approval records for those project products that have met their quality criteria
C.
Define the structure of the project management team
D.
Produce the Project Plan with resource and schedule information
all answers appear green, but which one is correct? is it A?
viewed on an Ipad, safari
0
0
It is A
1
0
The answer A is right, Managing Successful Projects With PRINCE2, Section 6.3.1
2