PRINCE2 Exam Questions

which are they?

There are two time driven controls in PRINCE2, which are they?

A.
Highlight and End Stage Reports

B.
Highlight and Checkpoint Reports

C.
Checkpoint and End Project Reports

D.
Highlight and Lessons Reports