Which activity takes place within the Managing a Stage Boundary process? seenagape 9 years ago Which activity takes place within the Managing a Stage Boundary process? A. Take corrective action within the limits of a stage’s tolerance B. Produce an Exception Plan C. Authorize a Stage Plan for the next stage D. Produce Highlight Reports ← Previous question Next question →