Identify the missing words in the following sentence. When planning the next stage, the
Project Manager needs to review and, if necessary, update the [ ? ] with regard to external
resources or suppliers.

A.
project management team and/or role descriptions
B.
Configuration Item Records
C.
Business Case
D.
Project Brief
Explanation:
The answer A is right, Managing Successful Projects With PRINCE2, Section 17.4.1