PRINCE2 Exam Questions

What product is reviewed by the Project Manager as part of progress assessment to determine whether

What product is reviewed by the Project Manager as part of progress assessment to determine
whether a Work Package is performing to the agreed cost and time tolerances?

A.
Highlight Report

B.
Checkpoint Report

C.
Exception Report

D.
Off-specification