What name is given to the permissible deviation allowed above and below a plan’s target for ti

What name is given to the permissible deviation allowed above and below a plan’s target for time
and cost without escalating the deviation to the next level of management?

A.
Concession

B.
Tolerance

C.
Contingency

D.
Allowance