In the PRINCE2 Quality review technique, who would most likely carry out the role of administrator: seenagape 11 years ago In the PRINCE2 Quality review technique, who would most likely carry out the role ofadministrator: A.Project manager B.Project support C.Team Manager D.Project Assurance ← Previous question Next question →