In the PRINCE2 Quality review technique, who would most likely carry out the role of administrator: seenagape 8 years ago In the PRINCE2 Quality review technique, who would most likely carry out the role ofadministrator: A. Project manager B. Project support C. Team Manager D. Project Assurance ← Previous question Next question →