If a project’s benefit tolerance is forecast to be exceeded, to whom should this be escalated seenagape 9 years ago If a project’s benefit tolerance is forecast to be exceeded, to whom should this be escalatedto for a decision? A. Executive B. Corporate/programme management C. Senior User D. Senior Supplier ← Previous question Next question →