Identify the missing words in the following sentence.During the Initiating a Project process
the [?] before a project is authorized.

A.
Project Brief is assembled and approved
B.
project approach appropriate for delivering a project is selected
C.
minimum necessary is done to decide if a project is worthwhile
D.
aim is to establish sound foundations to achieve a successful project
The answer is right, Managing Successful Projects With PRINCE2, Section 14.1