PRINCE2 Exam Questions

Identify the missing words in the following sentence, The six aspects of project performance to be m

Identify the missing words in the following sentence, The six aspects of project performance
to be managed are [?] costs, timescales and scope,

A.
benefits, quality, risk,

B.
change, quality, progress,

C.
benefits, progress, risk,

D.
benefits, customers, quality,