Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels
of [?] to reflect the needs of the different levels of management involved in a project,

A.
Management strategies
B.
Plan
C.
Stakeholder interests
D.
Time-driven controls
The answer B is right, Managing Successful Projects With PRINCE2, Section 7.2.3