How does the Progress theme assist the Project Board to assess project viability at regular interval

How does the Progress theme assist the Project Board to assess project viability at regular
intervals?

A.
Sends regular Checkpoint Reports to the Project Board

B.
Only one management stage is authorized at a time

C.
Creates Exception Reports when tolerances are forecast to be exceeded

D.
Reports to the Project Board during project closure