Identify the missing words in the following sentence. An objective of the Closing a Project
process is to ensure that provision has been made to address [?] through follow-on action
recommendations.

A.
the handover of products
B.
open issues and risks
C.
the measurement of benefits NOT yet realized
D.
the release of resources
Explanation:
The answer B is right, Managing Successful Projects With PRINCE2, Section 18.2
3
0