When are tolerances for a Work Package agreed?

A.
As work on each product within the Work Package begins
B.
Once ail products have been developed and approved
C.
When accepting a Work Package
D.
When the Stage Plan is authorized by the Project Board
The answer C is right, Managing Successful Projects With PRINCE2, Section 16.4.1