You need to view only the task name, start and finish dates, percentage of work completed, and a Gan

You need to view only the task name, start and finish dates, percentage of work completed,
and a Gantt chart. What should you do?

A.
Create a custom filter and a custom view.

B.
Create a custom table and a custom group.

C.
Create a custom filter and a custom table.

D.
Create a custom table and a custom view.

Explanation: