A project plan is published to Microsoft Office Project Server 2007. A fixed work task that is scheduled to take 4 days will really take 5 days. Without changing the remaining work on the task, you need to reschedule the task to take 5 days. The revised task must still appear in Microsoft Office Project Web Access on the timesheets of the assigned resources. What should you do?
A.
Change the finish date of the task, and then save the project plan.
B.
Change the actual finish date of the task, and then republish the assignments.
C.
Change the duration of the task to 5 days, and then republish the assignments.
D.
Change the duration of the task to 5 days, and then save the project plan.