You need to have Project automatically reschedule Task A if Task B finishes earlier or later than sc

You are managing two projects in Microsoft Office Project Standard 2007. Task A in Project Alpha is dependent on Task B in Project Beta. You need to have Project automatically reschedule Task A if Task B finishes earlier or later than scheduled. What should you do?

A.
Display the Task Drivers pane to manage the automatic rescheduling.

B.
Display the external predecessors and successors in both project plans.

C.
Create a master project that includes both project plans, and then create a cross-project link.

D.
Create a master project that includes both project plans, and then assign the same calendar to both tasks.