You need to ensure that Project issues a warning if you use resources that are not in the shared res

You create a shared resource pool in Microsoft Office Project Standard 2007. You are allowed to use only resources from the shared resource pool in your projects. You need to ensure that Project issues a warning if you use resources that are not in the shared resource pool. What should you do?

A.
Turn on the Project Guide.

B.
Activate the Advice about errors option.

C.
Deactivate the automatic addition of new tasks and resources.

D.
Start the Planning Wizard, and then choose the Advice about scheduling option.