Microsoft Exam Questions

You need to create a view that will fulfill the company’s requirement for identifying schedule

You need to create a view that will fulfill the company’s requirement for identifying schedule delays in advance. What should you do?

A.
In Microsoft Office Project Web Access, add the Finish variance column to the Tasks Summary view in the Project Center.

B.
In Microsoft Office Project Web Access, create a custom project field named Schedule status that uses formulas and graphical indicators. Add this field to the Summary view in the Project Center.

C.
In Microsoft Office Project Web Access, create a custom task field named Schedule status that uses formulas and graphical indicators. Add this field to the Tasks Summary view in the Project Center.

D.
In Microsoft Office Project Professional 2007, create a custom task field named Schedule status that uses formulas and graphical indicators. Add this field to the Gantt Chart Table:
Summary view in the project.