PrepAway - Latest Free Exam Questions & Answers

You have an Exchange Server 2007 environment. Your nightly backups are scheduled to run on Mailbox servers at

You have an Exchange Server 2007 environment. Your nightly backups are scheduled to run on Mailbox servers at 1:00

PrepAway - Latest Free Exam Questions & Answers

A.
M. Each backup takes approximately four hours. Your maintenance window is currently set to start at 10:00 P.M. and to end at 3:00 A.M. You notice that online defragmentations are not finishing successfully. This operation typically takes 4.5 hours. You need to ensure that database

B.
Configure the maintenance window to end at 1:30 A.M.

C.
Configure the maintenance window to begin at 8:00 P.M.

D.
Configure the backups to begin at 10:00 P.M.

E.
Configure the backups to begin at 12:00 A.M.